In SAP QM as at ECC6.0 EhP6.0, for an Inspection Lot to be created as a Release Status successfully, which of thr following are mandatory ?

A)  Activation of an Inspection Type in thr Material Master. 
B)  A valid Sampling Procedure. 
C)  An Inspection Plan or Material Specification. 
D)  A QM Control key in thr Material Master QM data view. 
E)  Avalid Quality level.
.

2 comments:

  1. B) Sampling Procedure is mandatory for calculation of the sample size in thr Inspection lot for it to be released.
    C) Both Inspection Plan nor Material Specification is not necessary, and without them; Results Recoding is not required.
    D) QM control key is for MM for QM and even then it is not mandatory.
    E) Quality level is available when Dynamic Modification was activated for thr Material Inspection but it is not a mandatory feature.