Question no 3261 : TECO Maintenance Order

In SAP as at ECC6.0 EhP6, what happens when Maintenance Order is Technically Completed ?

(more than one answers)

A)  Capacities are released.
B)  Purchase Requisition is set with deletion flag.
C)  Purchase Order is set with deletion flag.
D)  Material Reservation will be set with deletion flag.
E)  Maintenance Notification linked to the Order must be Closed.
.

1 comment:

  1. A) All Capacity Load for Work Center will be released.
    B) All PR will be set Deletion Flag
    D) All Reservation will be set Deletion Flag

    What TECO will not do is:
    C) Set status to PO or Invoice
    E) Notification closure is optional at point of TECO