In SAP QM as at ECC6.0 EhP6, which of the following QM master data allow creation using Revision Level ?
(More than one answers)
A) Quality Info Record.
B) Inspection Plan.
C) Material Specification.
D) Inspection Method.
E) Master Inspection Characteristics.
.
(More than one answers)
A) Quality Info Record.
B) Inspection Plan.
C) Material Specification.
D) Inspection Method.
E) Master Inspection Characteristics.
.
Answer: A, B
ReplyDeleteC) Material Specification do not have facility for Change Number or Revision level. However via QS63, changes can be done for a key date.
ReplyDeleteD) Inspection Method also do not have facility for Change Number or Revision level. However, via QS32, a Version can be create for Inspection Method (similar to Master Inspection Characterstics). Also, via QS33, change using a key date is possible.
ReplyDeleteE) Master Inspection Characteristics do not have facility for Change Number or Revision Levels. However, via QS22, a Version can be created for the Master Inspection Characteristics. Also via QS23, change using a key date is possible.