In SAP PM as at ECC6.0 EhP6, which of the following connects One Maintenance Notification to Multiple Maintenance Orders in Maintenance Event Builder (MEB) ?
(only one answer)
A) Collective number.
B) Priority code.
C) Maintenance Activity Type.
D) Similar number range for both Document Types.
E) Revision.
.
(only one answer)
A) Collective number.
B) Priority code.
C) Maintenance Activity Type.
D) Similar number range for both Document Types.
E) Revision.
.
Before the introduction of MEB, Notification to Order link only allow 1:1 or Many:1 scenario. The MEB scenario is introduced to support 1:Many scenario. Since there is only one field to assign only one Maintenance Order in the Notification document; the Revision was introduced to make this 1:Many relationship possible only via MEB as at ECC6 EhP6.