In SAP QM as at ECC6.0 EhP6, which of the following are minimum requirement and must have setup for activating a material for quality inspection for goods receipt with reference to purchasing document?
(more than one answers)
A) Quality Info Record.
B) Material Master QM data view activation.
C) Activating QM Control key in the material master.
D) Activating an appropriate inspection type in the material master.
E) An Inspection Plan for the material.
.
(more than one answers)
A) Quality Info Record.
B) Material Master QM data view activation.
C) Activating QM Control key in the material master.
D) Activating an appropriate inspection type in the material master.
E) An Inspection Plan for the material.
.
Answer: B, D
ReplyDeleteA,D) Parameters in the QM control key determines if the Quality Info Record is required for Procurement Inspections. However, the use of QM Control key in the QM view of the material master is not mandatory.
ReplyDeleteE) An Inspection Plan nor a Material Specification are mandatory for Procurement inspection as the simplest inspection scenario is UD without RR.
ReplyDeleteAbove reference to A,D should have been A,C
ReplyDelete