In SAP PM ECC6.0 as of EhP5, the determination of Serial to Equipment Synchronization (which means whether the Serial number and Equipment should have the same number) is done via which of the following ?
(only one answer)
A) Serial Profile in the Material Master Plant Data Storage View 2.
B) Equipment Category configuration.
C) Asset Class configuration.
D) Serial Level in the Material Master Plant Data Storage View 2.
E) Asset-Equipment integration in the configuration.
.
(only one answer)
A) Serial Profile in the Material Master Plant Data Storage View 2.
B) Equipment Category configuration.
C) Asset Class configuration.
D) Serial Level in the Material Master Plant Data Storage View 2.
E) Asset-Equipment integration in the configuration.
.
The Serial Level field in the Material Mater Plant Data Storage 2 view decides if the Serial and Equipment Master numbers are to synchronize or can be different.
ReplyDeleteSerial Level " " (Blank) means Serialization within the stock material number.
Serial Level "1" means Keep Equipment number and Serial number synchronized.