In SAP PM ECC6.0 EhP5, in which of the following circumstance, the system sets the system status 'MPRT' (Modified After Print) to the operation ?
(more then one answers)
A) Changing the Operation Description.
B) Changing the Operation Work Time.
C) Assigning a new Component to the Operation.
D) Changing the quantity of an existing Component assigned to the Operation.
E) Changing the Work Center already assigned to the Operation.
.
(more then one answers)
A) Changing the Operation Description.
B) Changing the Operation Work Time.
C) Assigning a new Component to the Operation.
D) Changing the quantity of an existing Component assigned to the Operation.
E) Changing the Work Center already assigned to the Operation.
.
Answer: A, B, E
ReplyDeleteAs at ECC6.0 Ehp5, changing the component or adding components to a Printed Operation do not affect the system status of the Operation.