Question no 2367 : Checking Group assignment for Component Availability Check in the Maintenance Order

In SAP PM ECC6.0, in order to perform component availability check in the Maintenance Order, the Checking Group must be assigned to the __________________ .

(only one answer)

A)    Material Master in the Plant Maintenance Data View.
B)    Order Type and Planning Plant combination in the Customizing.
C)    Order Type, Planning Plant, and Production Supervisor combination in the Customizing.
D)    Material Master in the MRP 3 Data View.
E)    Work Center of the Operation in the General Data View.
.

5 comments:

  1. Checking Group can be found in the Material Master MRP3 view at the Plant Level.

    ReplyDelete
  2. However, Checking Rule (the other parameter) is assigned to the Maintenance Order Type plus Planning Plant in the Customizing. And the control is available for both creation and release of the Maintenance Order. This parameter decides among others the decision for availability check result. (eg: ignore, error, user decide)

    ReplyDelete
  3. The Checking Group PLUS the Checking Rule is then combined in a configuration to determine what should be included or excluded during the availability check. eg: should QI stock type be included or excluded during the AV check.

    ReplyDelete
  4. When you setup the Checking Group in the MRP3 view, you also need to fill up other data in the MRP1 and 2 views. However, if MRP is currently not relevant for the material, you can enter 'ND' (No Planning) as MRP type for the material and most fields will become option and you can proceed to filll up the desired Checking Group in the MRP 3 view.

    ReplyDelete