Question no 2366 : Scheduling Parameters for Maintenance Order

In SAP PM ECC6.0, which of the following settings are available when assigning Scheduling Parameter to the Maintenance Order Type ?

(more then one answers)

A)    Also include break times in scheduling.
B)    Ignore Queue time in scheduling.
C)    Allow start date in the past.
D)    Automatic carried out scheduling when saving the Maintenance Order. 
E)    Adjusting the Basic Dates to Operations Dates.
.

3 comments:

  1. Note the following configuration path for this:
    IMG - PM - PM/CS - Maint/Service Processing - Maint/Service Orders - Scheduling - Set Scheduling Parameters
    Planning Plant + Order Type (with Prod Scheduler "*")
    The following settings available:
    1) Adjust Basic Dates to Operation Dates
    2) Scheduling Type (Forward, Backward, Current, etc)
    3) Start in the Past
    4) Automatic Scheduling when Saving Order
    5) Automatic Log
    6) Break time inclusion when Scheduling

    ReplyDelete
  2. Reduction of Interoperation times such as Queue time is done through 'Reduction Strategy'. You may want to research what the 'Reduction Strategy' actually does and via which configuration assignment as it is possible example question from this topic.

    ReplyDelete