In SAP PM ECC6.0, you can assign the Factory Calendar in which of the following objects in SAP Plant Maintenance ?
(more then one answers)
A) Equipment.
B) Maintenance Task List.
C) Maintenance Plan.
D) Maintenance Work Center.
E) Mainteannce Planning Plant.
.
(more then one answers)
A) Equipment.
B) Maintenance Task List.
C) Maintenance Plan.
D) Maintenance Work Center.
E) Mainteannce Planning Plant.
.
Answer: C, D, E
ReplyDeleteC) You can Assign the Factory Calendar to Maintenance Plan Header at the Scheduling Folder.
ReplyDeleteD) All Work center allow Factory Calendar at the Capacity Header.
ReplyDeleteE) Both Maintenance Plant and Maintenance Planning Plant allow Factory Calendar.