This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, November 3, 2013

Question no 2085 : Net Indicator for BOM Costing

In SAP CO-PCP ECC6.0, what is the purpose of the Net Indicator in the BOM item ?

(only one answer)

A)   Includes in the cost estimate the operation scrap for each BOM item and not the assembly scrap in the material master record.
B)   Includes in the cost estimate the assembly scarp factor for each BOM item and not the assembly scrap in the material master record.
C)   Includes in the cost estimate the  assembly scarp factor for each BOM item and not the operation scrap in the material master record.
D)   Includes in the cost estimate the operation scrap for each BOM item and not the operation scrap in the material master record.
E)   Includes in the cost estimate the operation scrap for each BOM item and not the operation scrap in the Routing operation.
.

2 comments:

  1. If the Net indicator is set, the system includes in the cost estimate the operation scrap for each BOM item and not the assembly scrap in the material master record. If you define operation scrap, you must set the Net indicator.

    ReplyDelete