In SAP QM ECC6.0, the following processes allowed the setup of QM inspection EXCEPT ?
(only one answer)
A) Goods receipt without purchase order.
B) Goods receipt for consumable purchase order without material master.
C) Goods receipt for production order.
D) Stock transfer from plant to plant.
E) Goods receipt for repetitive orders.
.
(only one answer)
A) Goods receipt without purchase order.
B) Goods receipt for consumable purchase order without material master.
C) Goods receipt for production order.
D) Stock transfer from plant to plant.
E) Goods receipt for repetitive orders.
.
Answer: B
ReplyDeleteWithout material master for purchase orders, there is no inspection possible via the inspection lot.
ReplyDelete