This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, September 1, 2013

Question no 2022 : Cycle Set

In SAP PM ECC6.0, you use Cycle Set for which type of Maintenance Planning ?

(only one answer)

A)     Single-Cycle Time based Plan.
B)     Single-Cycle Performance based Plan.
C)     Strategy-Plan Time based.
D)     Strategy-Plan Performance based. 
E)     Multi-Counter Plan.
.

4 comments:

  1. The Cycle set in used for Multi-Counter Plan.

    ReplyDelete
  2. A,B) no strategy is require for single cycle MPs; this applies to single cycle time-based or single cycle performance-based.

    ReplyDelete
  3. C,D) a strategy with one unit of measure is required for time-based or performance based strategy plan. The strategy is required for the multi cycle definition but using one unit of measure for each strategy plan.

    ReplyDelete