In SAP PM ECC6.0, you use Cycle Set for which type of Maintenance Planning ?
(only one answer)
A) Single-Cycle Time based Plan.
B) Single-Cycle Performance based Plan.
C) Strategy-Plan Time based.
D) Strategy-Plan Performance based.
E) Multi-Counter Plan.
.
(only one answer)
A) Single-Cycle Time based Plan.
B) Single-Cycle Performance based Plan.
C) Strategy-Plan Time based.
D) Strategy-Plan Performance based.
E) Multi-Counter Plan.
.
Answer: E
ReplyDeleteThe Cycle set in used for Multi-Counter Plan.
ReplyDeleteA,B) no strategy is require for single cycle MPs; this applies to single cycle time-based or single cycle performance-based.
ReplyDeleteC,D) a strategy with one unit of measure is required for time-based or performance based strategy plan. The strategy is required for the multi cycle definition but using one unit of measure for each strategy plan.