In SAP PP as at ECC6.0 EhP6, choose a Strategy suitable for Planning at the Phantom level ?
(only one answer)
A) Strategy 19.
B) Strategy 29.
C) Strategy 39.
D) Strategy 49.
E) Strategy 59.
.
Answer: E
Phantoms are part of the BOM, but Phantoms are not to be produced. When planning is at the Phantom level, it is only used for Planning purpose only. The Sales Order will consume the Planned Independent Requirement of the Phantom Planned material. Backflush of the Phantom components is expected of and this will reduce the Phantom Planned Independent Requirement.
(only one answer)
A) Strategy 19.
B) Strategy 29.
C) Strategy 39.
D) Strategy 49.
E) Strategy 59.
.
Answer: E
Phantoms are part of the BOM, but Phantoms are not to be produced. When planning is at the Phantom level, it is only used for Planning purpose only. The Sales Order will consume the Planned Independent Requirement of the Phantom Planned material. Backflush of the Phantom components is expected of and this will reduce the Phantom Planned Independent Requirement.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.