This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, July 4, 2021

Question no 3857 : Source List for Source Determination

In SAP MM/PP MRP as at ECC6.0 EhP6, which of the following ensures the Source assigned in the Source List is recognized during MRP Run for Source Determination ?

(only one answer)

A)  Source List activation at the MRP Plant Parameter.
B)  Source List activation at the MRP Group Parameter.
C)  Source List activation at the MRP dat view in the Material Master.
D)  Source List activation in the Purchasing data view in the Material Master.
E)  MRP Relevant indicator for the Source in the Source List.
.

Answer: E

"1" for MRP Relevant.
"2" for Create Delivery Schedule for SA.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.