In SAP PP as at ECC6.0 EhP6, which of the following Strategy generates Production Order when saving a Sales Order in the Make-to-Order scenario ?
(only one answer)
A) 20.
B) 25.
C) 80.
D) 81.
E) 82.
.
Answer: E
the following are MTO scenario (no Req. type for PIR)
20 MRP run generates planned order to fulfil the Sales Order demand.
(only one answer)
A) 20.
B) 25.
C) 80.
D) 81.
E) 82.
.
Answer: E
the following are MTO scenario (no Req. type for PIR)
20 MRP run generates planned order to fulfil the Sales Order demand.
25 is for Variant Configuration.
80 is for Project Settlement for non-stock items.
81 generates Planned Order for Repetitive Scenario when save the Sales Order.
82 generates Production Order for Discrete Order Scenario when save the Sales Order.
82 generates Production Order for Discrete Order Scenario when save the Sales Order.
83 is Assembly processing with networks,