In SAP PM as at ECC6.0 EhP6, which of the following uses the Activity Rate and Confirmation to determine the actual cost in a Maintenance Order ?
(more than one answers)
A) PM01.
B) PM02.
C) PM03.
D) PM04.
E) PM05.
.
Answers: A, E
A) PM01 is Internal Operations.
B) PM05 is Internal Operations with Services (eg: a Subsidiary is performing the Maintenance Services).
Both PM01, PM05 uses the Activity Type and Activity Price to determine the Prices, and via Confirmation to derive the costs.