In SAP PP as at ECC6.0 EhP6, which of the following MRP run provides Interactive Delay Information for Decision Making ?
(only one answer)
A) Simulative MRP run.
B) Interactive MRP run.
C) Scope of Plan MRP run.
D) Regenerative MRP run.
E) Net Change MRP run.
.
Click "1 comment" for suggested solution
(only one answer)
A) Simulative MRP run.
B) Interactive MRP run.
C) Scope of Plan MRP run.
D) Regenerative MRP run.
E) Net Change MRP run.
.
Click "1 comment" for suggested solution
Answer: A
ReplyDeleteWhen executing MRP run suing "Simulative" indicator, the system calculates the delays and total delays for interactive decision makings.