In PP as at ECC6.0 EhP6, which of the following can use a Cost Collector to collect costs ?

(more than one answers)

A)  Repetitive Planned Orders.
B)  Planned Orders for Shop Floor Production.
C)  Production Orders.
D)  Planned Independent Requirement.
E)  Planning Scenario.
.

Click "1 comment" for possible solution.

1 comment:

  1. Answers: A, C

    A) REM Planned Orders cannot collect cost, it must use a Cost Collector.
    C) Production Order itself is a cost collector but via a special Order Type, it can also collect costs via a cost collector.