In PP as at ECC6.0 EhP6, which of the following can use a Cost Collector to collect costs ?
(more than one answers)
A) Repetitive Planned Orders.
B) Planned Orders for Shop Floor Production.
C) Production Orders.
D) Planned Independent Requirement.
E) Planning Scenario.
.
Click "1 comment" for possible solution.
(more than one answers)
A) Repetitive Planned Orders.
B) Planned Orders for Shop Floor Production.
C) Production Orders.
D) Planned Independent Requirement.
E) Planning Scenario.
.
Click "1 comment" for possible solution.
Answers: A, C
ReplyDeleteA) REM Planned Orders cannot collect cost, it must use a Cost Collector.
C) Production Order itself is a cost collector but via a special Order Type, it can also collect costs via a cost collector.