Question no 3697 : MRP Mechanics with BOM Explosion

IN SAP PP as at ECC6.0 EhP6, which of the following settings must present for the BOM Explosion step of the MRP run to take place ?

(more than one answers)

A)  An appropriate MRP Type.
B)  A BOM.
C)  A Routing.
D)  A Production Version.
E)  A Planning Horizon.
.

click "1 comment" for suggested answers.

1 comment:

  1. Answers: A, B

    A) MRP Type for CBP will not perform BOM Explosion, while MRP Type for MPS (M0, M1, series) or MRP (PD, P1, P2, series) are valid for BOM Explosion.
    B, C) Only BOM is desirable, Routing is not necessary.
    D) Production Version will lock in the BOM and Routing but not necessary for BOM Explosion at MRP run.
    E) Planning Horizon is not a mandatory setting for the BOM Explosion process.

    Do note that in S/4 system, the use of Production Version becomes Mandatory for Manufacturing Planning and Execution.

    ReplyDelete