In SAP MM as at ECC6.0 EhP6, which of the following is CORRECT about the Purchasing Contract ?

(more than one answers)

A)  Goods Receipt is possible with reference to a Contract.
B)  A Scheduling Agreement can be created with reference to a Contract.
C)  A Purchase Order can be created with reference to a Contract.
D)  A Contract item can generate into a Source List.
E)  A Contract can be saved without a Plant.
.

click (1 comment) for suggested answer

1 comment:

  1. Answers: B, C, D, E

    A) In MM, GR is not possible for PR, RFQ/Quotation or Contract. However, GR is possible for PO with release to a Contract or Delivery Schedules for Scheduling Agreements.
    B,C) A Contract can be for 3 years and each year a Scheduling Agreement can be released against the Contract where Delivery Schedules can then be planned with the SA. The same for Purchase Order to be released with reference to a Contract.
    D) Contract item can be generated to Source List as long as a Material/Materials is/are specified in the Contract, even for Material Group contracts (but Material must be set in the inclusion/exclusion list) for the Contract item.
    E) Both RFQ and Contract can be created without Plant.