In SAP MM as at ECC6.0 EhP6, which of the following is the response of SAP when entering a Material Master without an Accounting Data View in a Purchasing Order ?
(only one answer)
A) Abap Dump.
B) Request for Estimated Price.
C) No Response.
D) System disallow and Exits.
E) Request for Account Assignment.
.
click (1 comment) for suggest answer
(only one answer)
A) Abap Dump.
B) Request for Estimated Price.
C) No Response.
D) System disallow and Exits.
E) Request for Account Assignment.
.
click (1 comment) for suggest answer
Answer: E
ReplyDeleteMaterial Master without Accounting Data View will require Account Assignment Indicator in the Purchase Order and if Condition Records not found for the Material, a condition price has to be entered (unless it is a FOC item) but there are no Estimated Price in the Purchase Order.
In Conclusion, it is only technically necessary to have only the Purchasing Data View of the Material Master in order to create a Purchase Document of Consumable scenario (with Account Assignment).