In SAP PP as at ECC6.0 EhP7, which of the following are examples of Time Based Floats in an MRP run and Production Order creation ?

(more than one answers)

A)  Safety Time.
B)  Safety Stock.
C)  Dynamic Safety Stock.
D)  Float Before Production.
E)  Float After Production.
.

click (1 comment) for suggested answers

1 comment:

  1. Answers: A, D, E

    A) Safety Time moves all the dates earlier in the number of days of the Safety Time assigned in an MRP run.
    B, C) Both Static and Dynamic Safety stock deals with Quantity as buffers.
    D, E) When a Production Order is created, the Scheduling Margin Key's Floats will be used.

    All these floats are time buffers.