In SAP PM-QM as at ECC6.0 EhP6, which of the following links the Measuring Point to the Master Inspection Characteristics so that Calibration Results from the Result Recording are written automatically as Measurement Documents for the Measuring Point ?
(only one answer)
A) Inspection Point.
B) Dynamic Modification Rule.
C) Classification Characteristics.
D) Unit of Measure.
E) Inspection Type.
.
Answer: C
Measuring Point - Classification Characteristics - Master Inspection Characteristics
(only one answer)
A) Inspection Point.
B) Dynamic Modification Rule.
C) Classification Characteristics.
D) Unit of Measure.
E) Inspection Type.
.
Answer: C
Measuring Point - Classification Characteristics - Master Inspection Characteristics