In SAP QM as at ECC6.0 EhP6, the Stages in the Dynamic Modification Rule are linked to the Sampling Scheme's Lot Size table via which of the following ?
(only one answer)
A) Stage Change.
B) Inspection Severity.
C) Inspection Stage.
D) Sampling Instruction.
E) Inspection Rule.
.
Answer: B
The common key is the Inspection Severity that creates the Sampling Sizing rule in the Sampling Scheme and it is the LINK in the Stage change table within the Dynamic Modification Rule.