In SAP MM as at ECC6.0 EhP6, you can convert a Purchase Requisition to which of the following ?
(more than one answers)
A) RFQ.
B) Purchase Order.
C) Contract.
D) Delivery Schedule.
E) Another Purchase Requisition.
.
Answer: A, B, C, D, E
All of the above.
D) PR can be assigned to Scheduling Agreement and subsequently to Delivery Schedule via ME59N.
E) Copy PR to another PR.
(more than one answers)
A) RFQ.
B) Purchase Order.
C) Contract.
D) Delivery Schedule.
E) Another Purchase Requisition.
.
Answer: A, B, C, D, E
All of the above.
D) PR can be assigned to Scheduling Agreement and subsequently to Delivery Schedule via ME59N.
E) Copy PR to another PR.