Question no 3349 : Validity Period in Purchasing Document

In SAP MM as at ECC6.0 EhP6, which of the following Purchasing Document scenario, header Purchasing document contains the Validity Period ?

(more than on answers)

A)  Blanket PO.
B)  Consumable PO.
C)  Invoicing Plan PO.
D)  RFQ.
E)  Contract.
.

1 comment:

  1. Answer: A, C, E

    Blanket PO
    Invoicing Plant PO
    Contract
    Scheduling Agreement

    ReplyDelete