In SAP PP as at ECC6.0 EhP7, to plan MRP and execute a Production Order for a valuated material into MM-Inventory Management in SAP, which of the following data view in the material master is mandatory ?

(more than one answers)

A)  Purchasing data view.
B)  MRP data view.
C)  Work Scheduling data view.
D)  Accounting data view.
E)  Warehouse Management data view.
.

1 comment:

  1. Answer: B, C, D

    Purchasing view is for MM procurement, WMS data view is for LE-WM activation.