In SAP PM as at ECC6.0 EhP6, Cost Center is assigned to which of the following in PM Technical Objects ?

(more than one answers)

A)  Functional Location.
B)  Equipment.
C)  Work Center.
D)  Activity Type.
E)  Material Master.
.

1 comment:

  1. Answer: A, B, C

    A) FL at the Organization Tab (IL01, IL02, IL03)
    B) EQ at the Organization Tab (IE01, IE02, IE03)
    C) WC at the Costing Tab (IR01, IR02, IR03)