In SAP PM as at ECC6.0 EhP6, Cost Center is assigned to which of the following in PM Technical Objects ?
(more than one answers)
A) Functional Location.
B) Equipment.
C) Work Center.
D) Activity Type.
E) Material Master.
.
(more than one answers)
A) Functional Location.
B) Equipment.
C) Work Center.
D) Activity Type.
E) Material Master.
.
Answer: A, B, C
ReplyDeleteA) FL at the Organization Tab (IL01, IL02, IL03)
B) EQ at the Organization Tab (IE01, IE02, IE03)
C) WC at the Costing Tab (IR01, IR02, IR03)