In SAP ERP as at ECC6.0 EhP6, which of the following can be switch on or off in consideration for a Long Term Planning Scenario ?
(more than one answers)
A) Sales Order.
B) Safety Stocks.
C) Lot Size.
D) Factory Calendar.
E) Firmed Planned Orders.
.
(more than one answers)
A) Sales Order.
B) Safety Stocks.
C) Lot Size.
D) Factory Calendar.
E) Firmed Planned Orders.
.
When defining a Long Term Planning Scenario, the following can be switched:
ReplyDelete(not a complete list below)
. consideration of Sales Order
. switch-off MTO strategy
. switch-off Direct production.
. change the lot size key.
. firmed planned orders.
. firmed receipts.
. planned independent requirement version and date range.
. work center capacity version.
. BOM selection ID.
. dependent requirement for re-order point materials.
check MS31 for the complete control parameters.