In SAP Manufacturing as at ECC6.0 EhP6, which of the following in SAP ERP's Manufacturing can generate Independent Requirements ?
(more than one answers)
A) Sales and Operations Planning.
B) Distribution Requirements Planning.
C) Forecasting.
D) Master Production Scheduling.
E) Material Requirements Planning.
.
(more than one answers)
A) Sales and Operations Planning.
B) Distribution Requirements Planning.
C) Forecasting.
D) Master Production Scheduling.
E) Material Requirements Planning.
.
A) SOP via MD74, MD75 Transfer SOP Plans to Demand Management generates the Planned Independent Requirements.
ReplyDeleteC) You can access the Forecasting Tool to generate Planned Independent Requirement from within SOP Planning OR you can execute Forecasting run via MP30 and MP38 for Material with Forecasting view and Historical data to generate Independent Requirements.
ReplyDelete