In SAP PP Manufacturing as at ECC6 EhP6, which of the following characteristics correctly describes use of Strategy 70 ?
(more than one answers)
A) It is a Make-to-Stock Strategy.
B) It is a Make-to-Order Strategy.
C) It is designed to be assigned to a Sub-Assembly material.
D) Planned Independent Requirement is usually not allowed.
E) Dependent Requirement from the superior material will consume the Planned Independent Requirement.
.
(more than one answers)
A) It is a Make-to-Stock Strategy.
B) It is a Make-to-Order Strategy.
C) It is designed to be assigned to a Sub-Assembly material.
D) Planned Independent Requirement is usually not allowed.
E) Dependent Requirement from the superior material will consume the Planned Independent Requirement.
.
Answer: A, C, E
ReplyDeleteStrategy 70 is Planning at the Assembly level:
ReplyDelete. for MTS
. for Sub-Assembly
. Header material can be either MTS or MTO
. Header material's dependent requirement via MRP run will consume the PIR.
. The Goods Issue of the Sub-Assembly to the superior materials Production Order will reduce the PIR.