In SAP ERP Manufacturing MRP as at ECC6.0 EhP6, review the current planning scenario as presented by the graphics below and determine the expected MRP calculation results ?
(only one answer)
A) A Planned Order of 30 and Another Planned Order of 180.
B) A Planned Order of 210.
C) A Planned Order of 50 and Another Planned Order of 180.
D) A Planned Order of 60 and Another Planned Order of 120.
E) A Planned Order of 50 and Another Planned Order of 150.
.
(only one answer)
A) A Planned Order of 30 and Another Planned Order of 180.
B) A Planned Order of 210.
C) A Planned Order of 50 and Another Planned Order of 180.
D) A Planned Order of 60 and Another Planned Order of 120.
E) A Planned Order of 50 and Another Planned Order of 150.
.
Rule for Rounding with Minimum Quantity is if the initial Net Qty is below 50 then the system will suggest the minimum 50 and not Round to 60; but the rest of the fulfillment will be based on the Rounding number.