In SAP MM ECC6.0, a purchase requisition can be converted to which of the following purchasing document ?
(more than one answers)
(A) RFQ
(B) Planned order
(C) Purchase Order
(D) Scheduling Agreement
(E) Production Order
.
(more than one answers)
(A) RFQ
(B) Planned order
(C) Purchase Order
(D) Scheduling Agreement
(E) Production Order
.
Planned Orders are only generated from MRP run, and Production Order is not part of MM.