In SAP MM ECC6.0, select the appropriate sequence depicting the procurement cycle:
I PO processing
II Determination of requirements
III Invoice verification
IV Goods receipt
V Source determination
VI Vendor Selection
VII PO monitoring
VIII Payment processing
(only one answer)
(A) V, VI, II, VII, I, IV, III, VIII
(B) V, VI, II, I, VII, IV, III, VIII
(C) II, V, VI, VII, I, IV, III, VIII
(D) II, V, VI, I, VII, IV, III, VIII
(E) II, VI, V, I, VII, IV, III, VIII
.
I PO processing
II Determination of requirements
III Invoice verification
IV Goods receipt
V Source determination
VI Vendor Selection
VII PO monitoring
VIII Payment processing
(only one answer)
(A) V, VI, II, VII, I, IV, III, VIII
(B) V, VI, II, I, VII, IV, III, VIII
(C) II, V, VI, VII, I, IV, III, VIII
(D) II, V, VI, I, VII, IV, III, VIII
(E) II, VI, V, I, VII, IV, III, VIII
.
Answer: D
ReplyDeleteA simple question and no explanation is needed, starts with requirement and ends at Account Payable.