This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, November 24, 2010

Question no : 624 PM Execution Order External Service Work Center

PLM300 Plant Maintenance
Unit 05 Corrective Maintenance

Which of the following are characteristics of external services procurement scenario using work center to represent the external company ?
(more than one answers)

(A) A Blanket Purchase Order is to be created with validity dates.
(B) The cost center must have been assigned to the blanket PO.
(C) The costs of the services are recorded in the activity prices.
(D) Shop papers from maintenance order are send to the external company.
(E) Periodic invoicing will debit the cost center.
.

1 comment:

Note: Only a member of this blog may post a comment.