This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, November 24, 2010

Question no : 589 PM Execution Order Partial Confirmation

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Partial confirmation with the status “PCNF” status in Time Confirmation option allows which of the following process ?
(more than one answers)

(A) Partial Confirmation done can be partially reversed.
(B) Partial Confirmation done must be reversed in full.
(C) Full Confirmation “CNF” can be done in the following confirmation step.
(D) Additional costs can be posted but the account assignment data is fixed.
(E) Account assignment data is changeable but additional costs cannot be posted.
.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.