This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, November 24, 2010

Question no : 608 PM Execution Order Release

PLM300 Plant Maintenance
Unit 05 Corrective Maintenance

When the maintenance order is released:
(more than one answers)

(A) Material reservations are created.
(B) Material withdrawal is now allowed.
(C) Material availability check may be automatically performed by the system.
(D) Additional materials cannot be inserted to the maintenance order.
(E) Materials other than specified in the maintenance order cannot be withdraw for the maintenance order.
.

1 comment:

Note: Only a member of this blog may post a comment.