Question no : 591 PM Execution Order Breakdown Processing Options

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Which of the following processing options are possible the for Breakdown Maintenance scenario ?
(more than one answers)

(A) Completing the notification while technically completing the maintenance order.
(B) Completing the notification separately from the technical completion of the maintenance order.
(C) Partially confirmation of the notification.
(D) Partially confirmation of the maintenance order.
(E) Partially confirmation of the maintenance order’s operations.
.