This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, October 14, 2026

Question no 4243 : Item Category "M" in the Contract

In SAP S/4, select the CORRECT statement regarding the Contract item 10 below ?


(only one answer)

A) Item Category "M" can be implemented for both Quantity and Value Contract.
B) The PR item must have the same net price of 2 EUR as the Contract.
C) The PR item's UOM must be the same as in the Contract.
D) The PR item's Material Group in the PO item need not be the same to the Contract. 
E)  The PR item can be an Account Assignment item.
.

Answer: A, D, E

Characteristics of Item Category "M" (material Unknown)
    It can be used in "MK" or "WK" Contracts
    the UOM need not be the same as long as conversion factors are set
    the Material Group need not be the same in the PO item vs the Material Unknown Contact
    the Price need not be same in the PO item vs the Contract price
    Both Stocks and Consumable PRs are allowed