This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Saturday, October 31, 2026

Question no 4260 : Planned Delivery Costs Automatic Settlement

In SAP S/4, to be able to perform Automatic Settlement of Delivery Cost via MRDC (Automatic Delivery Costs Settlement), select the required Prerequisites ?


(more than one answers)

A)  Baseline date must be set at the Company Code of the Freight Vendor V02.
B)  Baseline date must be set at the Company Code of the Freight Vendor V01.
C)  Vendor Master "V02" must be set with "ERS" indicator.
D)  Automatic Settlement of Planned Delivery Costs configured for the Freight Vendor V02.
E)  Automatic Settlement of Planned Delivery Costs configured for the Freight Vendor V01.
.

Answer: A, D

Prerequisites for MRDC (Automatic Delivery Costs Settlement)
    IMG > MM > LIV > ERS > Specify automatic Settlement of Planned Delivery Costs
        Activate for combination Company Code + Pur.Org + Freight Vendor V02
    SM30 Table T196F
        Transaction Code MRDC with Default Document type "RE" (or other user defined)
    Freight Vendor V02
        Payment Term at the Company Code of the PO concerned

No comments: