Question no 4033 : PDS Transfer via CURTOADV_CREATE

In SAP Advanced Planning S/4 1909, which of the following are TRUE for PDS Transfer via CURTOADV_CREATE ?

(more than one answers)

A. A Production Version must be created for the Materials concerned.
B. The Production Version must have a valid Routing and a valid BOM.
C. The Production Version can be with a valid BOM and without Routing.
D. The Assembly must have an Advanced Planning view but MRP views are not necessary in the Material Master.
E. Only Target Version "000" Active Version can be transferred.
.

Answer: A, C

A) If a valid BOM with its components were to be transferred to Advanced Planning, not just just assembly but the components must have been activated for Advanced Planning before executing CURTOADV_CREATE.
B, C) As at 1909, A Production Version must exist but only a BOM is necessary and Routing is not mandatory for a successful PDS Transfer.
D) When activating a Material for Advanced Planning, MRP view becomes Mandatory.
E) Target Version other than "000" can be transferred.