Question no 4030 : Overall Release Strategy for Purchasing Documents

In SAP Material Management, which of the following Release strategy is possible in SAP MM Purchasing Document ? 

(only one answer)

A. Overall Release Strategy allowed in Purchase Requisition. 
B. Item level Release Strategy allowed in Purchase Requisition. 
C. Release Strategy is possible Header and Item level in the Purchase Order.
D. Only Release Strategy in the Header level is allowed for Purchase Orders. 
E. All of the above.
.


Answer: A, B. D
Overall Release Strategy for PR means all PR item must be approve before the PR can be converted to PO (or next follow-up document). 
For PO, RFQ, Contract, Scheduling Agreements, the Release Strategy is only at the Header Level. 