In SAP Production Planning & Execution integration with the WM system in ECC6 EhP8, which of the following depicts Pull list based on each Production/Process Order in a WM Warehouse System"
(only one answer)
(only one answer)
A. Crate parts.
B. Pick parts.
C. Release order parts.
D. Event-Driven Kanban.
C. Release order parts.
D. Event-Driven Kanban.
E. Storage Location Level.
.
Answer: B
A. Crate Parts are replenished using "Kanban Containers" and not via the Pull list.
B. Pick Parts are Pull list to pick parts based on each Production/Process order.
C. Release Order Part are picked based on a range of Production/Process order where the picking results is a total quantity.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.