In SAP Production Planning & Execution, which of the following MRP Elements can be displayed in the Stocks Requirements List ?
(more than one answers)
A. Fixed Stock Transfer Releases.
B. Production Orders.
C. Customer Deliveries.
D. Sales Quotations.
E. Scheduling Agreements Delivery Schedules.
Answer: A, B, C, E
Issues and Receipts are called MRP Elements.
Fixed receipts include the following elements:
(more than one answers)
A. Fixed Stock Transfer Releases.
B. Production Orders.
C. Customer Deliveries.
D. Sales Quotations.
E. Scheduling Agreements Delivery Schedules.
Answer: A, B, C, E
Issues and Receipts are called MRP Elements.
Fixed receipts include the following elements:
Purchase ordersPurchasing Scheduling Agreement schedule linesConsignment ordersConsignment SA schedule linesProduction ordersReceipt reservations
Planned receipts include the following elements:
Purchase requisitionsReceipt-related dependent requirements (dependent requirements of BOM items with a minus sign)Planned orders
Fixed issues include the following elements:
ReservationsStock transfer reservationsFixed stock transfer releases (from purchase orders, scheduling agreements)Customer ordersSales Scheduling agreements Delivery SchedulesOutbound Deliveries
Planned issues include the following elements:
Forecast requirementsDependent requirementsPlanned independent requirementsPlanned stock transfer releases (from purchase requisitions, planned orders)
In the standard IMG (configuration in MM or PP), there are a list of MRP Elements which can appear in the Stock Requirement list or MRP List; you cannot de-activate any MRP Elements and only changeable is the Abbreviation Text and MRP Element Text.
MRP Element that does not display in the S/R List or MRP List are:
MM RFQ or Quotation DocumentMM or SD ContractsSD Contract
SD Sales InquiryMM or SD Scheduling Agreements (without Schedule Lines)