This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, March 24, 2024

Question no 3993 : MRP Elements in Stocks Requirements Lists

In SAP Production Planning & Execution, which of the following MRP Elements can be displayed in the Stocks Requirements List ?

(more than one answers)

A. Fixed Stock Transfer Releases.
B. Production Orders.
C. Customer Deliveries.
D. Sales Quotations.
E. Scheduling Agreements Delivery Schedules.

Answer: A, B, C, E

Issues and Receipts are called MRP Elements.

Fixed receipts include the following elements:
Purchase orders
Purchasing Scheduling Agreement schedule lines
Consignment orders
Consignment SA schedule lines
Production orders
Receipt reservations

Planned receipts include the following elements:
Purchase requisitions
Receipt-related dependent requirements (dependent requirements of BOM items with a minus sign)
Planned orders

Fixed issues include the following elements:
Reservations
Stock transfer reservations
Fixed stock transfer releases (from purchase orders, scheduling agreements)
Customer orders
Sales Scheduling agreements Delivery Schedules
Outbound Deliveries

Planned issues include the following elements:
Forecast requirements
Dependent requirements
Planned independent requirements
Planned stock transfer releases (from purchase requisitions, planned orders)


In the standard IMG (configuration in MM or PP), there are a list of MRP Elements which can appear in the Stock Requirement list or MRP List; you cannot de-activate any MRP Elements and only changeable is the Abbreviation Text and MRP Element Text.

MRP Element that does not display in the S/R List or MRP List are:
MM RFQ or Quotation Document
MM or SD Contracts
SD Contract
SD Sales Inquiry
MM or SD Scheduling Agreements (without Schedule Lines)