In SAP MM/PP as at ECC6.0 EhP6, which of the following settings allow a material planned on a regular basis by MRP, even when there was no MRP
relevant change for this material and the planning file was not set ?
(more than one answers)
A) Run a regenerative planning run (processing key NEUPL).
B) Run a net change planning run (processing key NETCH).
C) Run a net change in the planning horizon planning run (processing key NETPL).
D) Setting “plan regularly” on the MRP type.
E) Setting "plan regularly" on the Plant Parameter.
.
Answers: A, D
A) One of the possible solution is to run a regenerative planning run (processing key NEUPL), however, with this key all the materials will be planned and this is a frequent cause of performance issues.
D) MRP type on the customizing transaction OMDQ where the flag “plan regularly” is set on customizing.
(more than one answers)
A) Run a regenerative planning run (processing key NEUPL).
B) Run a net change planning run (processing key NETCH).
C) Run a net change in the planning horizon planning run (processing key NETPL).
D) Setting “plan regularly” on the MRP type.
E) Setting "plan regularly" on the Plant Parameter.
.
Answers: A, D
A) One of the possible solution is to run a regenerative planning run (processing key NEUPL), however, with this key all the materials will be planned and this is a frequent cause of performance issues.
D) MRP type on the customizing transaction OMDQ where the flag “plan regularly” is set on customizing.