Question no 3789 : Consumption Based Planning

In SAP MM/PP as at ECC6.0 EhP6, which of the following are not Consumption Based Planning ?

(more than one answers)

A)  ReOrder Point Planning.
B)  Forecast-Based Planning.
C)  Time-Phased Planning.
D)  MRP.
E)  Long Term Planning.
.

Answers: D, E

MRP and LTP are for PP dependent-independent requirement.