Question no 3784 : Material Status for Control of Material Requirements

In SAP PP as at ECC6.0 EhP6, which of the following are Controls possible for Material Requirements via the Material Status ?

(more than one answers)

A)  Planned Independent Requirement maintenance.
B)  Forecasting run.
C)  MRP run.
D)  Long Term Planning run.
E)  SOP Planning table maintenance.
.

click "1 comment" to view possible soultion
 

1 comment:

  1. Answers: A, B, C, D

    Check "Material Requirements" segment in the Material Status configuration at OMS4.