Question no 3692 : Material for Storage Location

In SAP MM/PP as at ECC6.0 EhP6, which of the following to the setup to ignore the Material in a Storage Location to be included in MRP run ? 

(only one answer)

A)  Activate an appropriate MRP Type in MRP 1 data view.
B)  Activate the MRP Area in MRP 1 data view.
C)  Select an appropriate Special Procurement key in MRP 2 data view.
D)  Select an appropriate MRP Strategy in MRP 3 data view.
E)  Setup MRP 4 data view at the Storage Location with "Exclusion from MRP Planning".
.

Answer: E