Question no 3691 : Calibration Plan Pre-requisite

In SAP PM as at ECC6.0 EhP6, which of the following are the necessary setup for Calibration scenario for PM Equipment via PM-QM integration ?

(more than one answers)

A)  The correct Inspection Type assigned to the Maintenance Order Type.
B)  Maintenance Plan Category will Call Object "Inspection Lot".
C)  General Task List with Strategy Plan is Mandatory for Calibration scenario.
D)  General Task List with Inspection Point at the Header.
E)  Equipment Master activated for Calibration Planning.
.

Click on the "1 comment" button to check the Suggested answers


1 comment:

  1. Answers: A, D

    A, B) MP Category is "Maintenance Order" (which is assigned to the Inspection Type 14 for Calibration) so that when the MO is generated, it also links to an Inspection Lot.
    C) General Task List need not be for Strategy Plan, Single Cycle Plan is possible.
    D) An Appropriate Inspection Point at the General Task List Header is necessary.
    E) Activation in the Equipment or FL for Calibration Planning is not needed (no such setting).